Hi Experts,
I have created one time based single cycle maintenance plan.1 plan is missing after schedule.Scenario is given below.
Plan Time base single cycle
cycle/unit 2 months
Call Horizon 90%
Schedule period 2Years
Scheduling indicator Time-Key date
Cycle start date Same date as maint plan created
When i schedule in ip10 i am getting only 11 plans,intead of 12 plans.
Regards
Prashanth