Hi Experts,
I m trying to achieve Pco monitoring in SAP MII 14.0. I m refering following document:
http://help.sap.com/saphelp_pco21/helpdata/en/f2/b1d0e885284db2baabef7eea15373e/content.htm
I m able to do the Alert Configuration using active monitoring.
But what condition should i check in MII transaction or which parameter from remote monitoring will tell me that PCo is down?
I want to send e-mail once PCo is down.
I have enabled the active monitoring and configured the MII system and got test connecttion as success.
I am able to see the all projects in MII server . I configured the transaction and input variable (xml). After click on ok ,getting success message.
After that I could not see any trx in transaction manager.
I made dataserver connection to pco as error but still I could not see the configured trx in transation manager.
Pls suggest me to overcome this issue.
Configuration:
SAP MII 14.0
PCO 2.3 SP3
Regards,
Raj.